The City’s latest filing challenges allegations of retaliation, unequal treatment, and constitutional violations as the legal battle over a proposed Imperial Valley data center continues. The City has won an important environmental-review ruling, but it has not yet won a final dismissal of the amended federal lawsuit.
IMPERIAL COUNTY, Calif. — The legal battle surrounding a proposed large-scale data center in the Imperial Valley has entered another chapter, with the City of Imperial asking a federal judge to dismiss a developer’s amended lawsuit and prevent the case from moving forward.
On November 19, 2026, attorneys representing the City of Imperial and City Manager Dennis Morita filed a motion in the U.S. District Court for the Southern District of California seeking dismissal of all four claims brought by Imperial Valley Computer Manufacturing, LLC (IVCM).
The motion follows a significant victory for the City in a separate state-court proceeding, where an Imperial County Superior Court judge ruled that Imperial County could not treat the proposed data center’s grading permit as exempt from environmental review under the California Environmental Quality Act (CEQA).
The federal dispute raises additional questions about the City’s handling of the proposed development, including whether Imperial officials violated the developer’s constitutional rights while reviewing project applications, communicating with neighboring jurisdictions, and challenging County approvals.
The City maintains that its actions were lawful and that the developer has failed to establish a viable constitutional claim. The developer, according to allegations described in the City’s latest filing, contends that Imperial improperly obstructed its development efforts and retaliated against its exercise of protected rights.
The disagreement traces back to 2024, when IVCM began exploring development of a data center campus spanning property within the City of Imperial, the City of El Centro, and unincorporated Imperial County.
According to the federal pleadings summarized in the City’s November 19 memorandum, representatives of the developer met with Imperial Community Development Director Othon Mora in September 2024 to discuss whether a data center would qualify as a permitted use under the City’s industrial zoning regulations.
The developer alleges that it relied on those early discussions when deciding to purchase approximately 95 acres within Imperial.
On January 17, 2025, the developer sent plans involving three neighboring sites to City officials. A more detailed site plan for property near Imperial Avenue and Aten Road followed on February 28.
On March 4, the developer submitted a formal site-plan review application and paid the required fee.
The developer maintains that Mora initially indicated the project could qualify as a permitted industrial use. However, the City’s subsequent written review raised questions about that interpretation.
In an April 4 letter, Mora explained that data centers and their associated substations were not explicitly identified in the City’s zoning code. The City also requested clarification about the project’s land use and warned that environmental studies might be necessary.
The developer argued that the proposed data center fell within existing industrial zoning provisions, particularly those allowing business, professional, and research offices. Imperial officials disagreed with that interpretation.
By July 2025, the City had informed the developer that additional approvals would be required, potentially including a zoning text amendment, conditional use permits, and environmental review.
In correspondence described in the amended complaint, Mora identified several areas requiring evaluation, including water resources, air quality, transportation, greenhouse gas emissions, noise, energy consumption, and potential impacts associated with battery storage and electrical infrastructure.
The City initially suggested that a mitigated negative declaration might be appropriate if potential environmental impacts could be reduced sufficiently. It also warned that a full environmental impact report could be required if significant impacts could not be adequately mitigated.
An environmental impact report, commonly called an EIR, provides a detailed public assessment of a project’s potential environmental consequences, possible alternatives, and measures to reduce adverse impacts. The process can involve additional studies, public participation, and changes to a proposed development before certain approvals are granted.
On August 20, 2025, Mora reiterated the City’s position that the data center was not expressly authorized under the existing industrial zoning classification.
The following day, IVCM withdrew its pending application, explaining that it intended to pursue a ministerial approval process rather than the discretionary review required by Imperial.
Under a ministerial approval process, officials generally apply established standards without substantial discretionary judgment. Discretionary approvals involve greater governmental judgment and can trigger environmental review under CEQA.
After withdrawing its City application, IVCM pursued approvals for a separate data center site on approximately 75 acres of industrial land in unincorporated Imperial County.
The federal pleadings describe that County proposal as a 250-megawatt data center.
On September 4, 2025, County planning staff issued a site-plan review indicating that a data center within an enclosed building was an expressly permitted use under the County’s industrial zoning ordinance.
Meanwhile, the developer continued communicating with Imperial.
On September 9, it emailed the City several technical documents, including traffic, air pollution, geotechnical, environmental, and reclaimed-water materials, along with updated drawings.
The developer has characterized subsequent events as involving another application for approval. The City disputes that characterization, arguing that the developer never formally submitted a new application or paid another application fee after withdrawing its earlier request.
Imperial now relies on that disagreement in its federal defense, arguing that the developer cannot claim it was denied approval of an application that was never formally submitted.
The developer’s broader position, as reflected in the City’s memorandum, is that Imperial’s interpretation and administration of its zoning requirements improperly prevented the project from advancing.
The dispute eventually extended beyond zoning and environmental review to questions about water service.
Data centers can require substantial infrastructure for electricity and cooling, although their water consumption varies depending on their design and cooling systems.
The developer had discussed purchasing reclaimed water from Imperial while also pursuing arrangements involving El Centro.
According to the City’s November 19 filing, El Centro issued a conditional will-serve letter concerning potable water for a data center site within that city.
A will-serve letter generally communicates a utility provider’s willingness to provide service, often subject to conditions. The extent of the commitment depends on the language of the letter and any requirements that must be satisfied.
On November 26, 2025, Morita requested a copy of El Centro’s letter and indicated that Imperial would also be contacting El Centro.
The developer alleges that El Centro changed its position approximately two weeks later.
In its amended complaint, IVCM alleges, on information and belief, that Morita or City staff contacted El Centro and discouraged officials from committing water to the development.
However, the City’s memorandum points out that the developer also acknowledged not knowing what, if anything, was actually communicated between the two cities.
The City argues that the timing of events does not establish retaliation or improper interference.
El Centro subsequently issued a public statement indicating that it had made no decisions or commitments concerning the sale of reclaimed water for the project.
Imperial also did not issue the requested reclaimed-water will-serve letter.
The contents of any communications between officials in the two cities, along with their possible influence on water-service decisions, remain unresolved in the materials reviewed.
As the developer pursued its County project, Imperial officials began considering legal action.
The Imperial City Council discussed anticipated litigation in closed session on November 19, 2025. According to the federal pleadings, Morita retained outside counsel several days later concerning the proposed data center in unincorporated Imperial County.
On December 4, 2025, the City filed a petition in Imperial County Superior Court challenging the County’s issuance of a grading permit.
Imperial argued that the County had improperly treated the grading permit as a ministerial approval, allowing the project to proceed without the environmental review required under CEQA.
The developer was named as a real party in interest because the outcome could directly affect its project.
The City subsequently amended its petition on January 7, 2026.
The developer also questioned whether Imperial had properly authorized the litigation under California’s Brown Act, which governs open meetings and certain decision-making procedures for local public agencies.
On February 18, the Imperial City Council voted to ratify and approve actions associated with the state-court proceeding.
The City’s latest federal memorandum disputes the developer’s suggestion that this action authorized a separate lawsuit against IVCM.
On September 30, 2026, the Imperial County Superior Court adopted a decision granting the City of Imperial’s CEQA petition.
The court determined that the County’s grading permit approval was not ministerial and that the proposed project was not exempt from CEQA review.
The ruling required environmental review, including preparation and consideration of an environmental impact report.
For Imperial, the decision represented a significant legal victory, supporting its position that the County’s grading-permit process had failed to satisfy applicable environmental-review requirements.
The ruling also became an important part of Imperial’s defense against the developer’s federal constitutional claims, particularly allegations concerning the City’s decision to pursue litigation.
In federal court, IVCM has asserted four claims under 42 U.S.C. Section 1983, a federal law that permits certain lawsuits alleging violations of constitutional rights by government officials.
The first claim concerns procedural due process. The developer contends that it possessed a legally protected interest in project approval and that Imperial improperly deprived it of that interest without adequate procedures.
The second involves First Amendment retaliation. The developer alleges that City officials took adverse actions connected to its protected speech and petitioning activities, including actions surrounding water service and the City’s legal challenge to the County.
The third concerns equal protection. The developer argues that it was treated differently from other industrial development applicants without sufficient justification, a legal theory sometimes called a “class-of-one” equal protection claim.
The fourth seeks to hold the City itself responsible for alleged constitutional violations under principles established in the U.S. Supreme Court’s *Monell v. Department of Social Services* decision.
Before the latest motion, the federal court had already considered the City’s challenge to the developer’s original complaint.
On November 2, 2026, U.S. District Judge Janis L. Sammartino dismissed the original complaint but permitted the developer to amend it.
The developer subsequently filed its First Amended Complaint, narrowing the named defendants to the City of Imperial and Morita.
The City’s latest memorandum emphasizes a finding from the November 2 decision concerning Imperial’s state-court litigation.
According to the memorandum, the federal judge determined that the City had probable cause to file its petition challenging the County’s grading permit.
The City argues that this finding undermines the developer’s allegations that Imperial used litigation as a form of unconstitutional retaliation.
In its November 19 filing, the City asks Judge Sammartino to dismiss the amended complaint under Federal Rule of Civil Procedure 12(b)(6).
That rule permits a court to dismiss claims that fail to state a legally sufficient basis for relief. When considering such a motion, the court generally assumes the truth of well-pleaded factual allegations and evaluates whether those allegations plausibly support a recognized legal claim.
Imperial’s attorneys argue that the developer had no guaranteed right to project approval because the City’s zoning regulations required officials to exercise discretion when reviewing the proposed data center.
According to the City, a developer cannot establish a protected entitlement to approval when local officials retain lawful discretion to grant, deny, or condition that approval.
The City also maintains that IVCM failed to pursue available administrative appeals or state-law procedures to challenge the City’s decisions.
Under Imperial’s zoning code, certain Planning Director decisions may be appealed to the Planning Commission within 10 calendar days. The City argues that the developer failed to use that procedure and has not adequately explained why it was unavailable.
The developer’s amended allegations, as described in the memorandum, challenge whether the relevant decision was properly issued by the Planning Director and whether the City followed the procedures required under its own zoning regulations.
Imperial further argues that the developer has not established a plausible connection between its protected activities and the actions it characterizes as retaliation.
Regarding water service, the City contends that IVCM’s allegations rely on speculation about communications with El Centro.
Imperial maintains that Morita’s request for El Centro’s conditional will-serve letter was consistent with the City’s ongoing consideration of reclaimed-water service. The City’s attorneys also suggest that Imperial was reluctant to make a commitment before determining whether the County project would undergo environmental review and public scrutiny.
Regarding the state-court lawsuit, the City points to its successful CEQA challenge and the federal court’s earlier probable-cause finding.
The City also invokes the Noerr-Pennington doctrine, which generally protects legitimate efforts to petition governmental bodies, including certain litigation activities.
Imperial argues that its successful state-court petition falls within that protection and that the developer has failed to establish circumstances that would remove the lawsuit from its scope.
The equal protection claim presents another disagreement over the treatment of industrial development applications.
The developer has identified other industrial uses and developments as potential comparisons, including livestock facilities, feed yards, cement manufacturing, fertilizer manufacturing, warehouses, and a recycling operation.
Imperial responds that many of those uses are expressly identified in its zoning code, while the proposed data center involves substantially different infrastructure and environmental considerations.
The City specifically addresses Konnection Recycling, which received a similar-use determination, arguing that recycling operations are more closely related to manufacturing activities already permitted under the industrial zoning provisions.
Imperial maintains that the developer has not identified another comparable data center or industrial project with similar electrical requirements, water demands, and battery-storage components that received more favorable treatment.
The City argues that these differences provide a reasonable basis for requiring additional review.
Imperial also challenges the developer’s municipal liability claim, arguing that the absence of an adequately alleged underlying constitutional violation prevents IVCM from holding the City responsible under Monell.
The motion separately addresses Morita’s potential personal liability.
The City argues that Morita is entitled to qualified immunity, a legal doctrine that can protect government officials from individual civil damages liability when their conduct does not violate clearly established federal rights.
According to the City’s attorneys, Morita’s communications concerning water service, his failure to provide a finalized will-serve letter, and his verification of the City’s state-court petition do not establish violations of clearly recognized constitutional protections.
The November 19 motion also asks the federal court to dismiss the amended complaint with prejudice.
If granted in full, that would end the developer’s current claims in the district court without another opportunity to revise the complaint, although appellate options may remain.
The City argues that the developer has already been given an opportunity to amend its allegations and failed to correct the deficiencies identified in the earlier proceeding.
Its attorneys point out that IVCM filed its amended complaint just three days after the November 2 dismissal order, arguing that the revisions did not meaningfully address the court’s concerns.
The federal judge will determine whether the amended allegations are legally sufficient and whether any further amendment should be permitted.
The dispute has also raised broader questions about development oversight in the Imperial Valley, particularly as communities consider proposals involving substantial electricity infrastructure, water resources, and industrial land.
The environmental-review ruling establishes that the County’s grading permit was subject to CEQA requirements. The federal proceedings address the developer’s allegations concerning Imperial officials’ conduct and the constitutional protections applicable to local development decisions.
Several questions remain relevant to residents following the controversy, including what communications occurred between Imperial and El Centro concerning water service, whether the developer submitted a legally sufficient replacement application, and how consistently Imperial applied its zoning requirements to comparable developments.
The environmental review will also provide an avenue for examining the County project’s potential effects on water supplies, electrical infrastructure, air quality, transportation, and surrounding communities.
For residents, the outcome could influence how future large-scale industrial proposals are evaluated, how local governments coordinate across jurisdictional boundaries, and how the public participates in decisions affecting the region.
A hearing on the City’s latest motion is scheduled for February 4, 2027, at 1:30 p.m., before Judge Janis L. Sammartino in the U.S. District Court for the Southern District of California.
The court may dismiss some or all of the developer’s claims, permit additional proceedings, or issue another ruling addressing the sufficiency of the amended complaint.
As of November 20, 2026, the November 19 motion remains pending.
The City has secured an important environmental-review ruling and is now seeking to bring the developer’s federal lawsuit to an end. The next decision will help determine whether the constitutional allegations can proceed and which issues, if any, remain before the federal court.
For the Imperial Valley, the controversy continues to place local development policy, environmental oversight, and government accountability under public scrutiny.
Sources: U.S. District Court for the Southern District of California, Imperial Valley Computer Manufacturing, LLC v. City of Imperial et al., Case No. 3:26-cv-00128-JLS-LR, including the November 19, 2026 motion to dismiss and supporting memorandum (Docs. 25 and 25-1), the request for judicial notice (Doc. 25-2), and the September 30, 2026 Imperial County Superior Court ruling in Case No. ECU004457. The November 2 federal order and developer’s amended complaint are discussed where described in the reviewed filings. See the newest docs here.